Heating
First, heat our drill rods for 3 to 4 hours within the hardening furnace.
Thermal Insulation
After heating is completed, these drill rods will be put into a quench tank for thermal insulation.
Tempering and Cooling
The drill rod will then be heated in a tempering furnace for 6 to 8 hours at a temperature range from 500℃ to 600℃. After that, it will be cooled in a tank at a temperature range from 30℃ to 40℃.
Nitriding
Nitriding is available upon request. It helps reduce the risk of scratching and extend the lifespan of our products.
Straightening
The thick-walled HDD drill rod is being straightened by our hydraulic machine. We use a clamp set, a dial indicator and a hydraulic jack to perform straightening operation.
Microstructure Testing
A pregrinder, a polishing machine and a cutting machine are used to test the microstructure of our product.
Wuxi Geotec Geological Equipment Co., Ltd.
Add.: No.113,Jiao Shan Road,Yangjian Machinery Industrial Park,Xishan,Wuxi,Jiangsu, 214107, China
Tel.: +86-510-88552380
Fax:
+86-510-88552380
+86-510-88552788